Laborers work.

Attending masons and jobbing.

Work to be done at Yaquina L.H. in August 1871.

Last coat of plaster to be completed. Base to be put down. Mouldings placed on doors, windows and base. Mantels to be set. Doors to fit and hang. Closets, pantry, service room, storerooms and oilroom to fix up. Stair rails to hang. Painting outside of house. Roof and fence to be completed. Inside painting to be commenced. All work to be completed except some painting inside and work about the tower.

The deck plate, lantern lens, etc. will not reach Yaquina before the 15 of September and making allowance for contrary winds the Light House will be completed about the 15th of October.