Vol 631 Tramway Winch LH Reports 1884 and 1885

14
Indexed

14

Office of the Light House Engineer Thirteenth District Portland, Oregon Dec. 4th 1884

To the Chairman Of the Light House Board Washington, D.C. Sir: In compliance with the Board’s request in letter of 10th ult., transmitting plan of store-house for mineral oil, I have the honor to submit the following list of light stations that should be supplied with such houses. Point-No-Point, W.T. (4th Order) A small room was partitioned, off in the barn and arranged for the storage of mineral oil, but it is considered unsafe. A brick house, 12’ x 11’ 10”, is recommended at an estimated cost of $1201.83

Last edit about 7 years ago by Wjhoward

Vol 348 Engineer Reports 13th Dist. 1873 and 1874 CF Exhibted YB Discontinued

5
Indexed

5

Supported decayed joists on south side of 1” of 2” floors of Keeper’s dwelling with girders and posts. Replaced outside cellar doors. Commenced running Fog Signal during foggy weather- Inspected Station and made estimates for thorough renovation repairs. Ediz Hook Lt Station, W.T. Inspected Station & made rough plans & estimate for Repairs. New Dungenness Lt Station, W.T. Inspected Station, and made plans & estimates for work of c-reading Steam Fog Signal Smith Island Lt Station, W.T. Indspected & made estimates for repairs Admirarlty Head LH Station, W.T. Inspected and made estimaties for thorough repairs, and rough plans. Very respectfully, Chairman Light-House Board, Henry M Robert Washington DC Maj of Eng’rs & LH Eng’r Thirteenth District

Last edit about 7 years ago by Wjhoward
6
Indexed

6

Office of the Light House Engineer Thirteenth District Portland, Oregon, Sept 9, 1873

SIR: I have the honor to make the following Report of Operations for the month of August 1873. Cape Foulweather Lt Station, Ogn Completed work on Lt-House & lantern, instructed keepers to exhibited the light for the first time on the night of August 20”. New Dungenness Lt Station, W.T. Completed detail plans and estimates of fog signal house. Purchased materials and sent men in charge of Supt of repairs, to erect fog whistle. Make contract for boiler for Fog Signal. Probable Operations for September Commence building house and cistern. Complete transportation and hauling of material. Admiralty Head Lt Station, W.T. Probable operations for September. Commence painting dwelling. Columbia River LH Station, Ogn Begin building Road in September, if plan forwarded is approved by Light House Board. Point no Point LH Station, W.T. Begin in September building road and clearing land of heavy timber, if Report of April 30th is approved by the Light-house Board. Very Respectfully, Chairman Light-House Board, Henry M Robert Washington DC Maj of Eng’rs & L.H. Eng’r

Last edit about 7 years ago by Wjhoward