YH LH location and building Vol. 311

94

94

Cape Hancock Light Station, Wash. Ter.Continued work on, and inspected Light Keepers Dwelling

Probable Work in December

Completion of Lights Keepers Dwelling

Cape Flattery Light Station, Wash. Ter.

Landed at Neah Bay about 100 tons freight, continued storm preventing landing on Tatoosh Island.

At Tatoosh Island, the Engine and Fog Apparatus have been cleaned and stored for rainy season; the cement and bricks have been hoisted to the top of the Island and put under shelter; and operations partially suspended until more favorable weather.

Probable Work in December

Further excavation for cistern, and canoe transportation of materials from Neah Bay (7 miles) to Tatoosh Island, so far as the weather will permit. Though it is probable that work can not be prosecuted till some time in January.

Very respectfully,Your obedient servant,Henry M RobertMaj. of Eng'rs & L.H. Eng'rThirteenth District

361

Last edit 9 months ago by DReade
102

102

Cape Hancock Light Station, Wash Ter.

Completed, finally inspected, & turned over to Light Keeper Light Keeper's Dwelling.

Probable work in January

Make drawings of plans & elevation of Light Keeper's Dwelling as completed.

Cape Flattery Light Station, Wash. Ter.

No work done

Probable Work in January

Resume work on excavation of Cistern and transportation of materials from Neah Bay, if the weather permits.

Very respectfully,

Your obedient servant,

Henry M RobertMaj. of Eng're & L.H. Eng'rThirteenth District

370

Last edit 9 months ago by DReade
104

104

Cape Hancock Light Station, Wash TerMade drawings of Light Keepers Dwelling, as completed.Commenced plans for new oil house.

Probable Work in FebruaryComplete plans, & make estimate for new oil house.

Cape Flattery Light Station, Wash. Ter.Made arrangements for immediately resuming work on excavation of cistern & transportation of stores if weather permits.

Probable work in FebruaryExcavation of cistern. Transportation of stores from Neah Bay if weather permits.

Very respectfully,Your obedient servant,Henry M RobertMaj. of Eng'rs & L.H. Eng'r,Thirteenth District

372

Last edit 9 months ago by DReade
111

111

Office of the (Light House Engineer)Thirteenth District

Portland, Oregon May 3 (1872)

Chairman Light House Board,

Washington, D.C.

SIR:I have the honor to make the following Report of Operations for the month of March 1872.

Cape Foulweather Lt Station Oregon 1871-72Completed and Inspected one third of metal work for Tower.Work delayed by partial wreck of Schooner engaged in Transportation of Light House Materials: no loss to Light House Establishment. Surveyed Lt. Ho Reservation-Probable operations in April.Deliver materials. Commence work on foundation. Continuous Inspection

Cape Flattery Lt. Station Wash. Feb 1872Continued work on Cistern & Transportation of Materials from Neah Bay, but Through the want of mail communications have not yet received definite accounts of the amount of work.Probable Operations in April.Continue excavation and Transportation. Send men to erect Fog Signal.

Very respectfully,Your obedient servent,Henry M Robert Maj. of Eng'rs & L.H. Eng'rThirteenth District.

386

Last edit 9 months ago by DReade
119

119

Office of the Light (House Engineer - text obliterated)Thirteenth DistrictPortland, Oregon, June 24th (1872)

Chairman Light House Board,Washington, D.C.

SIR:

I have the honor to make the following Report of Operations for the month of May:Cape Foulweather Lt. Station Oregon 1871-72 completed metal work for Light House + Inspection of the same. Commenced transportation by land of materials from Newport. Commenced work on foundation for tower.Probable Operations for JuneTransport materials from Portland, San Francisco, & Newport. Continue work on Tower Foundation.

Cape Hancock Lt. Station, Wash. TertyFurnished materials for painting Tower.

Cape Flattery Lt. Station, Wash. Terty.Sent Light House Clerk & men to complete the erection of Steam Fog Signal. Found excavation of cistern completed, & much time expended in transportation of materials from Neah Bay, with only half a dozen canoe loads actually delivered on the Island of materials landed at Neah Bay. Brought 20 Tons of Sand from main land, also the balance of lumber from Neah Bay and the "Warm House" at which point much of the lumber had been landed from a wrecked raft in April.

395

Last edit 9 months ago by DReade
120

120

Hoisted to the top of the Island & carried to S.H. Site the Brick and balance of materials. Graded around Cistern & for the Wood & Engine House. Completed House except inside work & painting. Emptied Cistern of water 10 or 12 times, the depth of water dipped out running from one to seven feet; & the constant streams of water interfering materially, with the progress of the work. Completed Brick work on cistern, except the floor. Erected Fog Signal apparatus & kept in operation nearly one week instructing the Light Keeper & one assistant in its management.Probable Operations for JuneComplete House, & paint it. Floor, Plastering, & Top of Cistern. Deliver 25 Tons of coal in Wood House, from Neah Bay. Make drawings of completed work. Inspect Light House.Probable General Work for June-Careful Inspection of the following Light Stations, with reference to improvements & repairs; Cape Flattery, Ediz Hook, New Dungeness, Smith's Island, + Admiralty Head.

Very respectfully,Your obedient servant, Henry M. RobertMaj. of Eng'rs & L.H. Eng'r,Thirteenth District.

396

Last edit 9 months ago by DReade

1871-1872 keeper selection and LH building Vol. 336

12

12

THIRTEENTH DISTRICT

Portland, Oregon, July 9, 1872

Chairman Light House Board,

Washington, D.C.

SIR:

I have to submit the following Report of Operations for June: Cape Foulweather Lt. Station, Oregon. Shipped metal work to San Francisco, as no vessel could be chartered from Portland to Foulweather except at exorbitant rates. Shipped stone work & miscellaneous freight from San Fran- to the Cape; also all the L.H. materials (per??? schooner) from Newport to the Cape. Completed grading about L.H. Site, and collection of sand. Continued work on Tower foundation. Transported all materials at top of Tramway to L.H. Site. Probable Operations for July. Transportation of materials from San Francisco. Continue work on Tower. Commence work on Light Keeper’s Dwelling. Cape Flattery Lt. Station, Wash. Ter. Completed & painted wood & engine house, & cistern. Delivered 25 tons coal from Neah Bay, in Wood House. Made drawings of completed work. Inspected Lt. Station. Left Fog Signal in charge of Keeper and one assistant, who did not wish further instruction in its management. Cistern has no water, and the Whistle can not be regularly blown (except for practice) early??? winter, without great expense. Will transmit at an early day, in-

Last edit almost 2 years ago by lkarnatz

Coast Guard District narrative histories 1945

83

83

Coast Guard Lighthouse, Lookout Tower, etc.) placed a limitation on beacon performance in this sector. A second site ("B") elevated 300 ft. was also considered for the RACON Station. The site was only a mile from Moon Island Airport, with a road for access and with a mast height of 50 ft. It afforded operation seaward for surface craft up to a distance of 24 miles (line of sight) which, although the site was 9 miles inshore of Point Chehalis, Washington, provided a better range extending to seaward 3 miles beyond that of "A".

A third site ("C") was considered where the temporary Army installation had been set up. However, this location had many disadvantages as the elevation was 40 ft. less than that of "B". A large elevated water tank presented a problem in the matter of radio shadow. The property at "C" was owned by the City of Hoquiam, Washington, and the owner of the adjacent land objected to the building of a tall structure. The only disadvantage that appeared at the "B" site was the fact that a Civil Aeronautics Administration Light Beacon Tower, which had been established there, had a tall structure which produced a shadow. However, the various structures could be located so that the shadow would occur to the east where it would not affect an overall performance. The Commander of the Northwestern Sector, Western Sea Frontier, was heartily in favor of the "B" site for, in addition to the reasons stated above, a considerable number of Navy flights used the route via Moon Island when en route between Astoria, Oregon, and such points as Shelton, Seattle, Whidbey Island and Arlington in the State of Washington. The Commander, Northwest Sector also urged that, should a place be made by the Coast Guard in this location, the Army be requested to remove their temporary installation to avoid unnecessary duplication, and probable confusion to pilots. In January, 1945, the Chief of Naval Operations directed the Coast Guard to take action to install a RADAR Beacon at Site "B". The Commander, Naval Air Bases, 13th Naval District was also of the opinion that the site should be at this particular location.

Before work had progressed to any extent, the Army announced that it proposed to decommission the RACON installation at Cape Meares (Oceanside), Oregon, Neah Bay, Washington, and Hoquiam, Washington. Immediately the District Coast Guard Officer requested Headquarters' approval for these stations to be taken over by the Coast Guard, 13th Naval District. Approval granted, a survey was made of the Cape Meares (Oceanside) RACON as well as the one at Neah Bay, Washington. The Cape Meares location consisted of one YJ and one YK equipment located in a rubberized Quonset type

-63-

Last edit over 2 years ago by Wjhoward
84

84

hut situated on a hill at an elevation of approximately 335 ft. The only access to the station was by a foot path up a steep hill through a wooded area. All supplies and equipment were packed up and down this path. There was no emergency power line and no sanitary facilities or drinking water at the hut. It was definitely determined that that location was unsatisfactory from the standpoint of adequacy of equipment, lack of space for additional equipment or spares, lack of space for enlarging the present building and lack of accessibility. With this in mind, a survey was made of the Cape Meares Light Station, Tillamook, Oregon, with the idea of relocating the RACON equipment on Coast Guard property where adequate space was available at an elevation at approximately 325 ft. However, coverage to the eastward was restricted to high altitudes by a ridge, 150 ft. higher than the station. The coverage was comparable with that obtained at the present location. The Army had located in this particular site for security reasons and, as the war ended the necessity for such security, the more accessible position gained favor. In addition to other difficulties, when the Army RACON personnel were withdrawn, there were no facilities for messing, other than in the town of Oceanside, Oregon, (one mile distant) which Army Medical authorities had condemned as unsatisfactory from the standpoint of cleanliness. All things indicated that Cape Meares Light Station was the ideal place to move the equipment.

A similar inspection was made at the Neah Bay Army RACON Station which consisted of two YJ units and two CPN-3 Units located on top of a 1430 feet hill in a square wooden building. The station was accessible by a road constructed by the Army. The grade was steep, the road rough, but it was normally open the year around except for occasional falling of trees across the road. An attempt had at one time been made to top the nearby trees, but the Indians in the area objected. It was thought that satisfactory coverage could be given aircraft and perhaps surface craft without topping the trees, but as a flight had never been made it was not possible to make an accurate deduction. At that time, Army personnel were subsisted and quartered at a camp near the village of Neah Bay, Washington. It was necessary for personnel to be housed in the Neah Bay Indian Village, 6 miles from the RACON Station.

For reasons of inaccessibility and because good coverage was not provided for surface craft, a survey was conducted to determine whether or not adequate coverage for both air and surface craft could be given from a location on Tatoosh Island, Washington, in the vicinity of the former Navy RACON which had earlier been discontinued there. On 1 September, however, the station at Neah Bay, Washington, and at Cape Meares (Oceanside, Oregon) were transferred from

-64-

Last edit over 2 years ago by Wjhoward