1860_WhitcherSheldonChapel2_2010_010_007

OverviewTranscribeVersionsHelp

Facsimile

Transcription

Status: Needs Review

Mount Auburn Cemetery Corporation

To Whitcher, Sheldon & Co Dr

1856

Correct
"Calculated at the time
it was ordered and written
on the back of the my copy of
the contract. GS."


For Rebuilding Chapel -- per contract -- $16.900.00
70 feet in length Coping @ 2.75 192.50
27 [feet in length] back moulding 54.00
correct charge one foot Extra thickness of Brick work in portions of front & Rear walls 360.00
[total] $17.506.50
Contra [Cr?]


1855. April 9 By Cash $3.000. --
["] June 5 " " 2.000. --
["] " 9 " " 3.000. --
["] August 10 " " 4.000. --
1856. March 22 " " 1.500. --
["] June 23 " " 500. --
["] August 23 " " 1.000 -- 15.000.
$2.506.50
To Mr G.W. Bond Treasurer --
Pay to Whitcher Sheldon & Co Two thousand dollars
($2000.) of the above bill on account

Jacob Bigelow}
Charles C. Little} Building committee on the Chapel

Feb. 7, 1860. Pay the balance
which is $506.50

[in pencil] $78

Jacob Bigelow}
Charles C. Little} Building committee