Goodman 7,056 Concrete
McGilvray 61,900 Stone
Vulcan 6,987 Iron
Hettinger 18,345 Carpenter
Gladding McBeau 7,495 Tile
$101,783
Contracts approved for the Chemical Labr'ty
Untitled Page 2
Original Estimated Cost of Library & Assembly Hall, Construction Sheet No. 1
[columns]
Contracts ......................... || Amount of || Payments .... || Payments yet to be ........................................ || contract .... || made by J.L.S.|| made by J.L.S.
McGilvray Stone Co. - Stone Work || 70,380. || 70,380. || ---
E. A Hettinger - Carpenter Work .. || 19,870. || 19,870. || ---
Jos. F. Forderer - Roofing ............. || 7,050. || 7,050. || ---
E. F. Jones - Structural Iron ........... || 6,960. || 6,960. || ---
Freight on Structural Iron ............. || 983.20 || 983.20 || ---
Demichelis Schuh & Co. - Marble .. || 13,208. || 13,208. || ---
Freight on Marble ......................... || 2,899.47 || 2,899.47 || ---
Winslow Bros. & Co. - Iron Railing .. || 1,825. || 1,825. || ---
Wybro Hendy & Co. - Electric Wiring || 3,000. || 3,000. || ---
Shepard Bros. - Plumbing ............... || 674. || 674. || ---
Cement ......................................... || 12,604.25 || 12,604.25 || ---
Gladding McBean & Co. Tiling ........ ||1,076.90 ||1,076.90 || ---
..................................................... || 140.530.82 || 140.530.82 || ---
The above total $140,530.82 represents what the buildings were estimated to cost as per contracts signed by Jane L. Stanford. This amount added to amount necessary for Extras viz: $62,043.45 as shown on sheet No. 2 represents a Total expenditure in above to buildings of $202.573.87
Untitled Page 3
APR 3 1900
Sheet No. 2.
[columns]
----------- || Amount of Bills || Payments made by J.L.S || Payments yet to be made by J.L.S
McGilvray Stone Co. - Extra Stone Work ............. || 19,3799.82|| 19,379.82 || ---
E. A. Hettinger - Extra Carpenter Work .............. || 4,284.05 || 4,284.05 || ---
E. F. Jones - Extra Iron Work ............................. || 179.80 || 179.80 || ---
Smith & Young - Alpine Plaster ......................... || 615 || 615 || ---
W. W. Montague - Heating Plant ....................... || 575.80 || 575.80 || ---
Wybro Hendy Co., - Electric Light Fixtures ........|| 327 || 327 || ---
J. & R. Lamb - 3 windows ................................. || 1500 || 1500 || ---
Ingerson & Glasser - setting 3 windows ............. || 55 || 55 || ---
John De Leunn - 2 statues ................................. || 275 || 275 || ---
Riley & Gambarin - Scagotolia Columns ............ || 180 || 180 || ---
Dunham Carrington & H. Co. - Pipe, Hdwe. etc. || 1,869.65 || 1,869.65 || ---
Teaming Gravel, Sand, etc. ............................... || 2,894.70 || 2,894.70 || ---
Shepard Bros. - Extra Plumbing ........................ || 304.30 || 304.30 || ---
John Stock Sons - Cold Air Ducts ........................|| 200 || 200 || ---
J. Whitehouse - Statue "Guttenberg" ................... || 280 || 280 || ---
Jos. F. Forderer - Extras ..................................... || 602 || 602 || ---
McGilvray Stone Co. - Stone for statues .............. || 298.50 || 298.50 || ---
Westinghouse Elect. & M. Co. - 2 converters ........ || 421.95 || --- || 421.95 (payment yet to be made)
Thos. Dat Co. - Elec. Light Fixtures ......................|| 1,293.13 || --- || 1,293.13 (payment yet to be made)
C. F. Weber & Co. - Chairs ................................... || 4,790.80 || 4,790.80 || ---
West Coast Appliance Co. - Lamps ....................... || 281 || 281 || ---
Home Mfg. Co. - Tables ....................................... || 744 || 744 || ---
Heywood Bros. - Chairs ....................................... || 307.90 || 307.90 || ---
Powell & Dean - Tables & Case ............................. || 500 || 500 || ---
F. W. Sherman - Shades ....................................... || 89.25 || 89.25 || ---
E. A. Hettinger - Shelving ..................................... || 1,507.40 || 1,507.40 || ---
Snead & Co. Iron Works - Book Stacks ................... || 13,487 || 13,487 || ---
Percy & Hamilton - Architects .............................. || 4,800 || 3,800 || 1,000 (payment yet to be made)
.................................................................. || 62,043.05 || 59,327.97 || 2,715.08
.................................................................. || 140,530.82 || 140,530.82 || ---
.................................................................. || 202,573.87 || 199,858 || 2,715.08
Untitled Page 4
APR 3 1900
Original Estimated Cost of Memorial Chapel - Construction.
[columns]
Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S
McGilvray Stone Co - Stone Work ..... || 147,661 || 12,000 || 135,661
Geo. Goodman - Concrete Work. ...... || 6,765 || 6,765 || ---
E. F. Jones - Iron Work ...................... || 12,842 || 4,000 || 8,842
J. & R. Lamb - Windows .................... || 30,000 || 4,000 || 26,000
Cement 4225. + 886.50 ...................... || 5,111.50 || 5,111.50 || ---
.................................................... --- || 202,379.50 || 31,876.50 || 170,503
Extras
Sundry Small Bills ............................. || 248.17 || 248.17 || ---
S. P. Co - Spur Track ........................... || 347.16 || 347.16 || ---
Antone Frilli - 3 figures ...................... || 1,200 || 600 || 600
Total - Contracts as above ................... || 202,379.50 || 31,876.50 || 170,503
...................................................... --- || 204,174.83 || 33,071.83 || 171,103
Untitled Page 5
APR 3 1900
Original Estimated cost of "Natural Sciences Building Construction"
[columns]
Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S
McGilvray Stone - Stone work ........... || 79,879 || 12,000 || 67,879
Geo. Goodman - Concrete Work ........ || 20,645 || 11,500 || 9,145
R.P. Hurlburt - Carpenter Work ......... || 32,000 || 225 || 31,775
Cement 3341+6500+1829 .................... || 11,670 || 11,670 || ---
Vulcan Steel Works - Cast Iron ........... || 2,780 || --- || 2,780
Carnegie Steel Works - Steel Work ...... || 6,120 || --- || 6,120
E.F. Jones - Erection Steel & Iron Work || 650 || --- || 650
..................................................... --- || 153,744 || 35,395 || 118,349
Extras.
Henry A. Schulz - Architect ................ || 3,300 || 3,300 || ---
Sundry Small Bills. .............................|| 272.29 || 272.29 || ---
A. Sonnicksen - Teaming .................... || 149.15 || 149.15 || ---
..................................................... --- || 3,721.44 || 3,721.44 || ---
Total contracts as above. .................... || 157,465.44 || 39,116.44 || 118,349