APR 3 1900

Original Estimated Cost of Memorial Chapel - Construction.

[columns]

Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S

McGilvray Stone Co - Stone Work ..... || 147,661 || 12,000 || 135,661

Geo. Goodman - Concrete Work. ...... || 6,765 || 6,765 || ---

E. F. Jones - Iron Work ...................... || 12,842 || 4,000 || 8,842

J. & R. Lamb - Windows .................... || 30,000 || 4,000 || 26,000

Cement 4225. + 886.50 ...................... || 5,111.50 || 5,111.50 || ---

.................................................... --- || 202,379.50 || 31,876.50 || 170,503

Extras

Sundry Small Bills ............................. || 248.17 || 248.17 || ---

S. P. Co - Spur Track ........................... || 347.16 || 347.16 || ---

Antone Frilli - 3 figures ...................... || 1,200 || 600 || 600

Total - Contracts as above ................... || 202,379.50 || 31,876.50 || 170,503

...................................................... --- || 204,174.83 || 33,071.83 || 171,103