Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

7 revisions
lkarnatz at Dec 18, 2017 07:32 PM

10

[[Portland, Oregon]] August 19th, 1872 (Stamped) [[Major H.M. Robert|H.M. ROBERT]], US Engineers. AUG 19 1872 Maj. [[Henry M. Roberts]] L.H. Engr. 13th L.H. Dist. Sir: In consequence of the unavoidable delays which have attended the construction of the Keepers Dwelling at [[Cape Foulweather Light House Station]], I am obliged to ask for a further extension of sixty days time in which to complete the work. Illegible stamp here??? Owing to the stranding of the [[schooner Elnorah]] at [[Yaquina Bay]], the vessel I had engaged to transport my materials from [[San Francisco]], and the inability of her owners to procure another vessel, I was compelled to make different arrangements for the transportation of my materials,

Portland, Oregon
August 19th, 1872
(Stamped) H.M. ROBERT, US Engineers. AUG 19 1872
Maj. Henry M. Roberts
L.H. Engr. 13th L.H. Dist.
Sir:
In consequence of the unavoidable delays which have attended the construction of the Keepers Dwelling at Cape Foulweather Light House Station, I am obliged to ask for a further extension of sixty days time in which to complete the work.

Illegible stamp here???

Owing to the stranding of the schooner Elnorah at Yaquina Bay, the vessel I had engaged to transport my materials from San Francisco, and the inability of her owners to procure another vessel, I was compelled to make different arrangements for the transportation of my materials,

10

[[Portland, Oregon]] August 19th, 1872 (Stamped) [[Major H.M. Robert|H.M. ROBERT]], US Engineers. AUG 19 1872 Maj. [[Henry M. Roberts]] L.H. Engr. 13th L.H. Dist. Sir: In consequence of the unavoidable delays which have attended the construction of the Keepers Dwelling at [[Cape Foulweather Light House Station]], I am obliged to ask for a further extension of sixty days time in which to complete the work. Illegible stamp here??? Owing to the stranding of the [[schooner Elnorah]] at [[Yaquina Bay]], the vessel I had engaged to transport my materials from [[San Francisco]], and the inability of her owners to procure another vessel, I was compelled to make different arrangements for the transportation of my materials,

Portland, Oregon
August 19th, 1872
(Stamped) H.M. ROBERT, US Engineers. AUG 19 1872
Maj. Henry M. Roberts
L.H. Engr. 13th L.H. Dist.
Sir:
In consequence of the unavoidable delays which have attended the construction of the Keepers Dwelling at Cape Foulweather Light House Station, I am obliged to ask for a further extension of sixty days time in which to complete the work.

Illegible stamp here???

Owing to the stranding of the schooner Elnorah at Yaquina Bay, the vessel I had engaged to transport my materials from San Francisco, and the inability of her owners to procure another vessel, I was compelled to make different arrangements for the transportation of my materials,