The plastering in the dwelling, the window blinds, and plank walk from dwelling to tower were repaired and some new branch walks were made.
Work by hired labor assisted by keepers.

543 – Cape Arago
The brush on the land cleared last spring was burned and the clearing away of the logs and residue left was commenced and nearly completed.

544 – Cape Foulweather
The iron work for the tramway car and winch were obtained and shipped to the station. The lumber for the tramway was obtained at Yaquina Bay and work commenced. Some minor repairs were made by the keepers to the dwelling occupied by the 2nd assistant keeper.