Estimate for section of 1st Class Seacoast Lights near Cape Foulweather, Oregon. Made by Major Robert L.H. Engr. 13th Dist - Portland Oregon. July 18

Masons work and materials

314,000 Brick 12.00 3768
895 Cement Barrels 5.00 4475
155 Lime Barrels 2.50 387.50
320 Sand and Gravel Cubic yards 2.00 640
15 Rubble - Random Cubic yards 11.333 170
5 Sills Granite 12.00 60
100 Lathing & Plastering Yards 6.50 50
275 Excavation Cubic yards 6.50 137.50
1000 Labor Masons Days 5.50 5500
1500 Labor Tenders Days 3.00 4500


Estimate Actual Cost.
Price Amount
Mason Work and Materials $19688