Original Estimated Cost of Library & Assembly Hall, Construction Sheet No. 1

[columns]

Contracts ......................... || Amount of || Payments .... || Payments yet to be ........................................ || contract .... || made by J.L.S.|| made by J.L.S.

McGilvray Stone Co. - Stone Work || 70,380. || 70,380. || ---

E. A Hettinger - Carpenter Work .. || 19,870. || 19,870. || ---

Jos. F. Forderer - Roofing ............. || 7,050. || 7,050. || ---

E. F. Jones - Structural Iron ........... || 6,960. || 6,960. || ---

Freight on Structural Iron ............. || 983.20 || 983.20 || ---

Demichelis Schuh & Co. - Marble .. || 13,208. || 13,208. || ---

Freight on Marble ......................... || 2,899.47 || 2,899.47 || ---

Winslow Bros. & Co. - Iron Railing .. || 1,825. || 1,825. || ---

Wybro Hendy & Co. - Electric Wiring || 3,000. || 3,000. || ---

Shepard Bros. - Plumbing ............... || 674. || 674. || ---

Cement ......................................... || 12,604.25 || 12,604.25 || ---

Gladding McBean & Co. Tiling ........ ||1,076.90 ||1,076.90 || ---

..................................................... || 140.530.82 || 140.530.82 || ---

The above total $140,530.82 represents what the buildings were estimated to cost as per contracts signed by Jane L. Stanford. This amount added to amount necessary for Extras viz: $62,043.45 as shown on sheet No. 2 represents a Total expenditure in above to buildings of $202.573.87