Status: Complete

APR 3 1900

Original Estimated cost of "Natural Sciences Building Construction"

[columns]

Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S

McGilvray Stone - Stone work ........... || 79,879 || 12,000 || 67,879

Geo. Goodman - Concrete Work ........ || 20,645 || 11,500 || 9,145

R.P. Hurlburt - Carpenter Work ......... || 32,000 || 225 || 31,775

Cement 3341+6500+1829 .................... || 11,670 || 11,670 || ---

Vulcan Steel Works - Cast Iron ........... || 2,780 || --- || 2,780

Carnegie Steel Works - Steel Work ...... || 6,120 || --- || 6,120

E.F. Jones - Erection Steel & Iron Work || 650 || --- || 650

..................................................... --- || 153,744 || 35,395 || 118,349

Extras.

Henry A. Schulz - Architect ................ || 3,300 || 3,300 || ---

Sundry Small Bills. .............................|| 272.29 || 272.29 || ---

A. Sonnicksen - Teaming .................... || 149.15 || 149.15 || ---

..................................................... --- || 3,721.44 || 3,721.44 || ---

Total contracts as above. .................... || 157,465.44 || 39,116.44 || 118,349