APR 3 1900
Original Estimated cost of "Natural Sciences Building Construction"
[columns]
Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S
McGilvray Stone - Stone work ........... || 79,879 || 12,000 || 67,879
Geo. Goodman - Concrete Work ........ || 20,645 || 11,500 || 9,145
R.P. Hurlburt - Carpenter Work ......... || 32,000 || 225 || 31,775
Cement 3341+6500+1829 .................... || 11,670 || 11,670 || ---
Vulcan Steel Works - Cast Iron ........... || 2,780 || --- || 2,780
Carnegie Steel Works - Steel Work ...... || 6,120 || --- || 6,120
E.F. Jones - Erection Steel & Iron Work || 650 || --- || 650
..................................................... --- || 153,744 || 35,395 || 118,349
Extras.
Henry A. Schulz - Architect ................ || 3,300 || 3,300 || ---
Sundry Small Bills. .............................|| 272.29 || 272.29 || ---
A. Sonnicksen - Teaming .................... || 149.15 || 149.15 || ---
..................................................... --- || 3,721.44 || 3,721.44 || ---
Total contracts as above. .................... || 157,465.44 || 39,116.44 || 118,349