Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

3 revisions
shashathree at Sep 24, 2021 10:13 PM

Untitled Page 5

APR 3 1900

Original Estimated cost of "Natural Sciences Building Construction"

[columns]

Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S

McGilvray Stone - Stone work ........... || 79,879 || 12,000 || 67,879

Geo. Goodman - Concrete Work ........ || 20,645 || 11,500 || 9,145

R.P. Hurlburt - Carpenter Work ......... || 32,000 || 225 || 31,775

Cement 3341+6500+1829 .................... || 11,670 || 11,670 || ---

Vulcan Steel Works - Cast Iron ........... || 2,780 || --- || 2,780

Carnegie Steel Works - Steel Work ...... || 6,120 || --- || 6,120

E.F. Jones - Erection Steel & Iron Work || 650 || --- || 650

..................................................... --- || 153,744 || 35,395 || 118,349

Extras.

Henry A. Schulz - Architect ................ || 3,300 || 3,300 || ---

Sundry Small Bills. .............................|| 272.29 || 272.29 || ---

A. Sonnicksen - Teaming .................... || 149.15 || 149.15 || ---

..................................................... --- || 3,721.44 || 3,721.44 || ---

Total contracts as above. .................... || 157,465.44 || 39,116.44 || 118,349

Untitled Page 5

APR 3 1900

Original Estimated cost of "Natural Sciences Building Construction"

[columns]

Contractors || Amount of Contracts || Payments made by J.L.S. || Payments yet to be made by J.L.S

McGilvray Stone - Stone work ........... || 79,879 || 12,000 || 67,879

Geo. Goodman - Concrete Work ........ || 20,645 || 11,500 || 9,145

R.P. Hurlburt - Carpenter Work ......... || 32,000 || 225 || 31,775

Cement 3341+6500+1829 .................... || 11,670 || 11,670 || ---

Vulcan Steel Works - Cast Iron ........... || 2,780 || --- || 2,780

Carnegie Steel Works - Steel Work ...... || 6,120 || --- || 6,120

E.F. Jones - Erection Steel & Iron Work || 650 || --- || 650

..................................................... --- || 153,744 || 35,395 || 118,349

Extras.

Henry A. Schulz - Architect ................ || 3,300 || 3,300 || ---

Sundry Small Bills. .............................|| 272.29 || 272.29 || ---

A. Sonnicksen - Teaming .................... || 149.15 || 149.15 || ---

..................................................... --- || 3,721.44 || 3,721.44 || ---

Total contracts as above. .................... || 153,465.44 || 39,116.44 || 118,349